Weekly Update Calslaan Oud 3
The week has flown by! With the sun shining and a great atmosphere, a lot of work has been done. At Calslaan Oud 3 the scaffolders have everything ready for the first window replacement next week. The weekend will bring…

The week has flown by! With the sun shining and a great atmosphere, a lot of work has been done. At Calslaan Oud 3 the scaffolders have everything ready for the first window replacement next week. The weekend will bring…

Preparations for the upgrade of Campuslaan Hoog are in full swing! During the information session on March 7, students received details about the renovation work, the schedule, and the relocation process. Those who attended will share this information with their…

At Calslaan Oud 3, work is in full swing. We have now reached the top floor, where the insulated walls are being installed. Thanks to the excellent coordination of the professionals, tasks are progressing smoothly and everything is on schedule.…

The Upgrade of Calslaan Oud 3 is progressing fast! Nearly all new window frames are in place, and inside, the professionals are busy with finishing work and installing the mechanical ventilation. We’re keeping up the pace.

Although the renovation work at Calslaan 3 is ongoing, Calslaan 1 is next on the agenda. We organized a room chat on January 23 to properly prepare the students. During this meeting, students were informed about the planned renovation work…

The Upgrade at Calslaan Oud 3 is progressing quickly! The bathrooms and toilets have been demolished, wall insulation has started, and work is underway on the façade and roof.

We’re underway! The building has been carefully covered, demolition work has started, and the exterior is being cleaned.

The new year starts on a promising note for around 35 residents of Calslaan Oud as their homes receive an exciting upgrade. The first phase includes seven residential buildings on the Calslaan, with the sustainability and renovation of one building…

The students of Calslaan Oud 3 cleaned out their building to make way for the Upgrade. They worked hard together. Surplus items ending up in the container. Thanks to all for your effort!

The holiday is over, and we’re gearing up for the big moving day on Wednesday, January 8! At Calslaan 3, a storage container and a waste container have already been placed to ensure everything runs smoothly.

Today, we rolled up our sleeves during the cleanup day for Calslaan Oud 3. Students worked hard to tidy up, and the container is now filled to the brim!

The first students have returned to their renewed home on campus! The pilot phase of the Campus Upgrade has been completed. On Thursday, November 28, they were given a walkthrough in the upgraded building and symbolically handed back the key…